Senior energy officials warned the Labor government that its multibillion-dollar race to lure data centres to Victoria posed a “major structural challenge” to the state’s electricity system.
asserted
race → warn → system
The secret internal documents, released to The Age under freedom of information laws before next Saturday’s election, come as powerful community campaigns have forced the major parties to rethink their support of the controversial industry.
asserted
campaigns → release → industry
The Department of Energy, Environment and Climate Action briefing warned the plan to attract up to $25 billion in investment in data centres could trigger a “step change” – a sudden surge in electricity demand – with potential implications for Victoria’s clean energy transition as ageing coal-fired generators retire.
uncertain
generators → warn → transition
“This pipeline of investment will require data centres to connect to the electricity grid rapidly,” the March 2026 briefing on managing large electrical loads to then energy minister Lily D’Ambrosio read.
asserted
briefing → require → D’Ambrosio
“While this presents an economic opportunity for Victoria, the scale of projected energy demand from Victoria’s data centre industry presents a major structural challenge for the state’s electricity system.”
asserted
scale → present → system
The briefing reveals the government lacked oversight of the looming surge, needing greater visibility to understand how mega-projects would “impact the grid individually and in aggregate”.
asserted
projects → reveal → aggregate
To close the blind spot, D’Ambrosio approved plans to force Victoria’s five power distributors – AusNet, CitiPower, Jemena, Powercor and United Energy – to alert her before offering grid connections to any project exceeding 30 megawatts.
asserted
D’Ambrosio → close → megawatts
Officials said the move was needed to manage risks tied to heavy electricity use, unlock the economic opportunity, and determine what policy changes were needed to “maintain energy affordability and security while continuing to reduce Victoria’s emissions”.
asserted
changes → say → emissions
The private advice came at the same time when the then premier Jacinta Allan was vowing to “ruthlessly” court data centre investment, with its approval processes applauded by industry lobbyists.
asserted
processes → come → lobbyists
The department’s warning on grid capacity was echoed by peak business bodies.
asserted
warning → echo → bodies
In a December 2025 letter to the Energy and Climate Ministerial Council, cited in the FOI release, the Australian Industry Group urged ministers to take urgent action to prepare for a full range of growth scenarios.
asserted
Group → cite → scenarios
‘The scale of projected energy demand from [the] industry presents a major structural challenge for the state’s electricity system.
asserted
scale → project → system
’DEECA briefing to former energy minister Lily D’Ambrosio
The group warned that energy users were increasingly concerned the pace of data centre expansion was outstripping the ability of governments and the energy sector to maintain “full situational awareness and respond in a timely way”.
asserted
pace → warn → way
Victoria University Energy Policy Centre director Professor Bruce Mountain said the state could not meet its 2035 deadline to phase out coal-fired power if the upper forecasts for data centre demand eventuated.
uncertain
forecasts → say → demand
“It could upend the energy transition in a huge way,” he said.
uncertain
he → upend → way
He said the government courted the tech giants without understanding the strain on the power network.
asserted
government → say → network
“It always struck me that there was a typical Victorian glossy brochure saying, ‘How wonderful, we’ve got this investment,’ sitting under the premier, without having the department or the relevant energy minister really knowing what this means,” Mountain said.
asserted
Mountain → strike → what
Months after the DEECA briefing, the strain on the grid played out publicly when fierce community backlash stalled high-voltage upgrades needed to support an expansion of NextDC’s West Footscray data centre.
asserted
backlash → play → centre
NextDC delayed the expansion and slashed its earnings forecast last month after residents blockaded electricity distributor Jemena from replacing timber power poles with towering metal structures through residential streets.
asserted
residents → delay → streets
Jemena paused the works in September.
asserted
Jemena → pause → September
A 2.4-gigawatt AI hub proposed for Plumpton in Melbourne’s outer west, first revealed by The Age, would demand more power at peak capacity than Loy Yang A – Victoria’s largest remaining coal power station – produces, enough to supply more than two million homes.
asserted
A → propose → homes
At peak capacity, the data centre site could increase the state’s average electricity demand by 50 per cent.
uncertain
site → increase → cent
“It would just be such a seismic shift were it to happen,” Mountain said.
asserted
Mountain → happen → ?
He warned households risked being stuck with the bill if network upgrades were built for speculative proposals that never materialised.
asserted
that → warn → proposals
“Those costs will be front-loaded,” he said.
asserted
he → load → ?
“The infrastructure will have to be incurred now, and there’s uncertain future consumption related to that.
asserted
infrastructure → have → that
If demand doesn’t arrive, [consumers] will still be paying for the infrastructure.”
asserted
consumers → arrive → infrastructure
A Labor spokesperson said a re-elected Carroll government would make data centres bring new renewable energy and storage with them and pay for the network upgrades they need.
asserted
they → say → upgrades
“The biggest risk to Victoria’s electricity supply is Jess Wilson, who wants to tear up the energy projects Victoria needs to keep the lights on,” the spokesperson said.
asserted
spokesperson → want → lights
Following community pushback, Labor has softened its stance of ruthlessly pursuing investment.
asserted
Labor → follow → investment
In September, Premier Ben Carroll announced a new plan imposing 150-metre buffer zones near homes and requiring developers to fund grid upgrades and bring their own renewable energy and storage – but projects already under assessment are exempt.
asserted
projects → announce → assessment
Opposition Leader Jess Wilson has trodden a cautious path on data centres, saying she supports the industry but wants investment directed to dedicated zones away from homes.
asserted
investment → tread → homes
“Labor’s approach to data centre development has been haphazard, allowing data centres to go ahead in inappropriate locations, and without consideration of what impact this will have on the energy grid,” a Liberal Party spokesperson said.
asserted
spokesperson → allow → grid
“Victoria can secure the benefits of this industry without compromising the liveability of our communities.
asserted
Victoria → secure → communities
Managed properly, data centres can drive down wholesale power prices and strengthen the stability of our grid.”
asserted
centres → manage → grid
Any incoming government will have to balance growing public backlash and strain on the grid against the economy’s increasing reliance on data centre construction.
asserted
government → have → construction
The recent pre-election budget update revealed that Victoria’s lacklustre economic growth is being “primarily driven by data centre investment” alongside renewable energy projects.
asserted
growth → reveal → projects
At NextDC’s annual general meeting on Friday, chairman Douglas Flynn argued Australia “would be nuts to cut off” investment in data centres.
asserted
Australia → argue → centres
Who knows.
asserted
Who → know → ?