A proposed data centre in regional Queensland, Australia, has received overwhelming opposition from residents, with 595 submissions objecting to the project or requesting a delay, compared with only two in support.
asserted
submissions → receive → support
The figures were disclosed in a filing lodged on behalf of developer Zerra DC, as reported by Reuters on November 20.
asserted
figures → disclose → November
The proposed Western Downs Digital Park, about 250 kilometres west of Brisbane, is expected to become one of Australia's largest computing facilities, with artificial intelligence company Anthropic signed as its anchor tenant.
asserted
Anthropic → expect → tenant
The filing recorded nearly 600 public submissions, including one neutral response.
asserted
filing → record → response
It also acknowledged that many residents had raised concerns about the project's potential effects on water resources, electricity supply, noise, roads and local housing.
asserted
residents → acknowledge → resources
The development has become a major point of debate over the infrastructure demands of large-scale artificial intelligence operations and the impact they could have on communities hosting them.
uncertain
they → become → them
Residents raise concerns over power, water and roads
asserted
Residents → raise → power
According to the filing, a significant number of submissions raised concerns about the scale of the development and its possible effects on the surrounding region.
uncertain
number → accord → region
Objectors questioned how much water the facility would require, whether its electricity demand could affect power prices and supply, and whether construction traffic would damage local roads.
uncertain
traffic → question → roads
Others raised concerns about noise and additional pressure on housing.
asserted
Others → raise → housing
The project is planned on farmland in the Western Downs region.
asserted
project → plan → region
Its proposed IT capacity is 1.44 gigawatts, which would make it one of the largest data centre developments in Australia.
asserted
it → propose → Australia
Around one-third of the submissions came from people living within 200 kilometres of the proposed site, according to the filing.
uncertain
third → come → filing
The project had received five objections in the month before Anthropic was named as its tenant on September 15.
asserted
Anthropic → receive → September
Most of the remaining submissions arrived between that announcement and November 11, when the local government closed the public consultation period.
asserted
government → remain → period
Developer outlines water and electricity plans
Zerra DC has said it takes the community's concerns seriously and that the submissions show residents want a greater say in how the development proceeds.
asserted
development → outline → say
The company said it was expanding its community engagement and planned to report on changes requested by the public.
asserted
it → say → public
On its official Western Downs Digital Park website, the developer describes the proposal as a master-planned digital and energy precinct with up to four phases of artificial intelligence-ready data centres.
asserted
developer → describe → centres
The project is being developed and will be operated by Zerra DC, with Australian Data Centres and Macquarie Capital serving as investors in the project.
asserted
Centres → develop → project
The developer says the facilities will use air-cooled technology rather than water-based evaporative cooling.
asserted
facilities → say → cooling
The developer has proposed using processed water from nearby gas operations during construction, subject to agreements and approvals.
asserted
developer → propose → agreements
During operations, it plans to rely primarily on rainwater harvesting and on-site recycling, rather than regular groundwater extraction.
asserted
it → plan → extraction
For electricity, the developer says the project will draw power from the national electricity market and procure a combination of supply from existing Queensland generators and new generation.
asserted
project → say → generators
The developer has also said it will cover the full cost of connecting to the grid, including any network upgrades required for the project.
asserted
it → say → project
However, this commitment does not establish that the development will have no wider effect on electricity supply or prices.
asserted
development → establish → supply
Anthropic lease puts project in spotlight
The proposed development is a major investment in regional digital infrastructure.
asserted
development → put → infrastructure
The developer's website describes Anthropic's agreement as a long-term lease commitment, although the project remains subject to planning and regulatory approvals.
asserted
project → describe → approvals
An earlier report by ABC News described the proposal as a $32 billion development comprising four data centres.
asserted
report → describe → centres
It reported that the first facility had been leased by Anthropic for potential use as early as 2027.
asserted
facility → report → 2027
The report also outlined the developer's plans for air cooling and rainwater collection, alongside questions from local residents and energy experts about the project's demands on the electricity system.
asserted
report → outline → system
The opposition comes amid wider debate in Australia about the resources required by data centres supporting artificial intelligence.
asserted
opposition → come → intelligence
Reuters noted that other projects have also faced resistance, including a proposed Sydney development that Goodman Group scrapped after public opposition and a Melbourne project by NextDC that was delayed amid concerns about energy use.
asserted
that → note → use
For the Western Downs Digital Park, the public submissions do not determine the outcome of the planning application.
asserted
submissions → determine → application
The proposal is still being assessed by the Western Downs Regional Council.
asserted
proposal → assess → Council
However, the response highlights the challenge facing developers seeking to build large AI infrastructure projects while addressing local concerns about their environmental, economic and practical effects.
asserted
response → highlight → effects