AI datacentres plan on-site power stations on huge scale despite climate risks, research reveals

Read the original at The Guardian ↗
Cite

Laville, S. (2026, November 11). AI datacentres plan on-site power stations on huge scale despite climate risks, research reveals. The Guardian. https://www.theguardian.com/world/2026/nov/11/ai-datacentres-on-site-gas-fired-power-stations

Dated from the outlet's own feed. Check the original for its byline.

The Guardian · collected 2026-11-11 · by Sandra Laville

Quick Summary

Researchers from BloombergNEF have found that developers of AI datacenters in the US, UK, and Europe plan to construct on-site gas power stations with a total capacity of 181GW due to delays in connecting to national grids. This planned rollout would emit about 345 million metric tonnes of CO2 annually in the US alone, equivalent to emissions from approximately 72.8 million fossil fuel cars. The research highlights the urgency for cleaner energy solutions as global leaders discuss electrification at the UN climate summit while datacenter developers prioritize quick access to power over environmental concerns.
Written by AI on 2026-11-11, from this article's own text only (the story summary below draws on all the coverage).

AI analysis

Story summary

Developers of artificial intelligence (AI) datacenters plan to build on-site fossil fuel power stations on a massive scale across the US, UK, and mainland Europe. According to research by BloombergNEF published on November 8, 2026, these datacenters aim to create 181GW of gas-fired capacity due to delays in connecting to national grids. This proposed on-site generation would emit approximately 345 million metric tonnes of carbon dioxide equivalent annually in the US alone, roughly equal to the emissions from about 72.8 million fossil fuel cars.

The research was released ahead of the 31st UN climate summit (COP31) in Turkey, where discussions focus on increasing electrification from clean sources. However, some key European leaders are attending an AI summit in Dublin instead. In the UK, Chancellor John Healey has given approval for datacenters to build temporary fossil fuel power stations while awaiting grid connections, raising concerns about climate impacts despite global efforts toward sustainability.

Written for “AI Datacenters Power Stations Plan” on 2026-11-11, grounded in this article and the 0 other(s) covering the same event.
Why this leaning score
The article's own words the score was based on. Each is quoted verbatim and was checked against the article text before being stored, so you can find it in the original.
Reading Leans strongly left (beta estimate) Confidence high
Leaning: leans strongly left for article 144713 (high confidence, 2 verified quotes) · logged 2026-11-11

Story

AI Datacenters Power Stations Plan
Technology · 1 article(s) covering the same event.

Compared with similar articles

This article reads leans strongly left and hedges 17% of its claims. Each row says how that neighbour differs.
CBC News
Centre further right than this Hedges 0 of 2 claims Outlet record 60/100
“The articles describe different aspects of AI data center development and concerns — protests against construction versus plans for on-site power stations.”
The Independent
Hedges 6 of 31 claims Outlet record 59/100
“The articles discuss different aspects of data center energy issues, with Article A focusing on a permitting bill in Congress and Article B reporting on research about planned on-site power stations for AI data centers.”
Daily Mail
Leans left further right than this Hedges 3 of 13 claims Outlet record 69/100
“The articles describe different aspects of concerns related to AI data centres, with Article A focusing on a research report revealing plans for on-site fossil fuel power stations and Article B reporting on government emails warning about potential energy shortages and increased costs in Scotland.”
How this article was measured signals, leaning charts, publisher record, byline, topics and claims

Signals How these are calculated →

Claims extracted
18
sentences that state something as happening or true
Uncertain
17%
3 of 18 hedged ("reportedly", "may", "according to")
Leaning
Leans strongly left
of the writing, not the subject · beta estimate
Publisher signals
65/100
The Guardian's corrections and hedging, across everything collected from it. Not a measure of accuracy.
Outlets on this story
1
Technology
Same framing elsewhere
1
articles that frame the event the way this one does
Analyzed 2026-11-11 · how these are computed

How this is being covered How these are calculated →

Article leaning vs. publisher reliability
Source leaning vs. consistency

Publisher

The Guardian · 3266 article(s) · 7 correction(s) detected
Running correction rate · 7 correction(s)

Who wrote this

Sandra Laville
6 article(s) here · 1 carrying a prediction
The research by BloombergNEF says this “speed to power” will – if the planned rollout happens – emit about 345m metric tonnes of carbon dioxide equivalent a year in the US, where 90% of on-site gas-fired power stations are planned.
Since then, however, he has overseen a series of announcements that have dismayed green-focused Labour MPs.
Emma Hardy, the water minister, indicated on Thursday that the environment could suffer in the ongoing drought.
Golf clubs and private schools could be barred from using mains water to irrigate playing fields and courses, and commercial car washes stopped from operating, under “non-essential use bans” being sought by the companies.
The published plan, which is open for consultation for 28 days, states that the developer will pay £2,675 per house – £42m in total – into the nature restoration fund to cover compensatory actions including fenland creation and restoration, a change in use of agricultural land to semi-natural habitat, catch-dyke restoration and deer management. But a previous draft of the EDP, seen by the Guardian, set the levy much higher.
Also by Sandra Laville
Nothing else under this byline is closely related to this article, so these are simply their most recent.
All 6 articles by Sandra Laville →

Topics

BloombergNEF European France Great Britain Turkey

Subjects

BloombergNEF ORG · 2× Daly PERSON · 1× Dublin GPE · 1× European NORP · 1× France GPE · 1× Future Energy Networks ORG · 1× Germany GPE · 1× Great Britain GPE · 1× Mark Daly PERSON · 1× Turkey GPE · 1×

Narrative

But the use of fossil fuel power generation on site is likely to be repeated by many more UK sites after the chancellor, John Healey, gave the green light for datacentres to build and run temporary on-site fossil fuel power stations while they wait for connections to the grid, as part of a so-called datacentre covenant.
framing: assertive · carried by 1 article(s) · first seen 2026-11-11
The research by BloombergNEF says this “speed to power” will – if the planned rollout happens – emit about 345m metric tonnes of carbon dioxide equivalent a year in the US, where 90% of on-site gas-fired power stations are planned.

Claims (18 extracted, 3 hedged)

Developers of AI datacentres plan to build on-site climate-destroying gas power stations on a huge scale to meet their energy demands, research reveals. asserted
research → plan → demands
Datacentres planned across the US, the UK and mainland Europe have proposals to build fossil fuel plants on-site to create 181GW of gas-fired capacity because of delays to connect to national grids, according to the findings. uncertain
Datacentres → plan → findings
The research by BloombergNEF says this “speed to power” will – if the planned rollout happens – emit about 345m metric tonnes of carbon dioxide equivalent a year in the US, where 90% of on-site gas-fired power stations are planned. asserted
% → say → stations
The report was published on Wednesday as global leaders gathered in Turkey for the 31st UN climate summit, where increasing electrification – ideally from clean sources – is a central part of discussions. asserted
increasing → publish → discussions
However, a number of key European leaders, including from France and Germany, will not be at Cop31, instead heading to Dublin where EU leaders will hold their first dedicated AI summit on Friday. asserted
leaders → include → Friday
Mark Daly, the head of datacentres and emerging tech at BloombergNEF, said: “The extraordinary economics around AI are making speed to power one of the most important priorities for defining constraints on datacentre developers. asserted
speed → emerge → developers
“The climate outcome will depend not only on how much electricity these facilities use, but on how quickly grids can connect them and whether power systems add cleaner generation alongside that demand. asserted
systems → depend → demand
By 2035, the electricity demand of AI datacentres was predicted to almost quadruple to 2,354 terawatt-hours – equivalent to 7% of global electricity demand – the report said. asserted
report → predict → demand
AI datacentres use a massive amount of electricity to power servers and cool equipment, and to run facility systems. asserted
datacentres → use → systems
Daly said while the developers of the future datacentres claimed their gas-fired power supplies would be temporary while they waited for grid connections, once they were online, the economics could encourage them to continue generating energy, creating a longer-term fossil-fuel lock-in risk. uncertain
economics → say → risk
The report said ensuring new datacentres were connected to the grid was the more sustainable option. asserted
datacentres → say → grid
Faster grid connections were crucial to limiting emissions impacts and locking in fossil fuel risk, it said. asserted
it → limit → risk
UK planned datacentres made more than 100 inquiries in 2024-5 to connect to gas as a result of delays in securing access to the electricity grid, according to Future Energy Networks, the representative body for the UK gas networks. uncertain
datacentres → plan → networks
For example, Wapseys Wood, Buckinghamshire and Quest Park, Bedfordshire are seeking to build their own on-site gas-fired power stations because of the long wait to connect to the grid. asserted
Wood → seek → grid
The datacentres are among the first to be fast-tracked through the government’s nationally significant infrastructure project regime, which allows developers to rapidly deliver major infrastructure, bypassing locally elected planning authorities. asserted
developers → track → authorities
But the use of fossil fuel power generation on site is likely to be repeated by many more UK sites after the chancellor, John Healey, gave the green light for datacentres to build and run temporary on-site fossil fuel power stations while they wait for connections to the grid, as part of a so-called datacentre covenant. asserted
they → repeat → covenant
Oliver Hayes, the head of policy and campaigns at Global Action Plan , said: “Private gas power stations for datacentres should be a red line for any government serious about climate action, so it’s shocking to see the chancellor give them his explicit backing. asserted
chancellor → say → backing
“No one seriously believes these gas power stations will be temporary – once they’re built, they’ll lock in high emissions for years.” asserted