Russia’s nuclear plants are ageing. Who will pay to dismantle them?

Read the original at Al Jazeera ↗
Cite

Makichyan, A. (2026, October 4). Russia’s nuclear plants are ageing. Who will pay to dismantle them? Al Jazeera. https://www.aljazeera.com/opinions/2026/10/4/russias-nuclear-plants-are-ageing-who-will-pay-to-dismantle-them?traffic_source=rss

Dated when The Aporia collected the article, usually within hours of publication. Check the original for its exact date and byline.

Al Jazeera · collected 2026-10-04 · by Arshak Makichyan

Quick Summary

The article highlights the risks associated with Russia's ageing nuclear power plants and the challenges in decommissioning them. It notes that while some reactors are over 50 years old, Russia continues to build new nuclear facilities abroad. Lithuania’s experience with shutting down Soviet-built reactors shows the high cost and prolonged timeframe of decommissioning: the process for Ignalina Nuclear Power Plant was estimated at €3.7 billion by 2020 but will take until 2049 to complete. Russia faces a similar challenge, with Rosenergoatom estimating a funding shortfall of approximately €18.7 billion out of an expected total cost of €21 billion for decommissioning 35 reactors. The article also mentions the growing radioactive waste legacy from Soviet times and new decommissioning efforts.
Written by AI on 2026-10-04, from this article's own text only (the story summary below draws on all the coverage).

AI analysis

Story summary

Russia's ageing nuclear power plants, some over 50 years old, pose significant decommissioning challenges that receive less attention than their potential threat to global security. While Russia promotes nuclear energy as a sustainable alternative and builds reactors in countries like Turkey and Bangladesh, it neglects the costly and complex process of dismantling its own outdated facilities. For instance, Lithuania was required to close two Soviet-built reactors at the Ignalina Nuclear Power Plant upon joining the EU; the first reactor closed in 2004 and the second in 2009, with the decommissioning costs estimated at over 3.3 billion euros ($3.7bn) by 2020, though only 49% of the work had been completed by then. The original schedule for completing the cleanup was set for 2038, but it is now expected to extend until at least 2049. This issue highlights Russia's historical pattern of downplaying nuclear accidents and their long-term impacts, as seen with the 1957 Mayak disaster, which remained concealed by Soviet authorities for over three decades, causing significant health and environmental damage.

Written for “Russian Nuclear Plant Dismantling Costs” on 2026-10-31, grounded in this article and the 0 other(s) covering the same event.

Story

📰 Russian Nuclear Plant Dismantling Costs
Environment · 1 article(s) covering the same event.

Compared with similar articles

Nothing to compare against. No article is close enough to this one for the pipeline to have linked or judged the pair.
How this article was measured signals, leaning charts, publisher record, byline, topics and claims

Signals How these are calculated →

Claims extracted
54
sentences that state something as happening or true
Uncertain
7%
4 of 54 hedged ("reportedly", "may", "according to")
Leaning
Leans left
of the writing, not the subject · beta estimate
Publisher signals
60/100
Al Jazeera's corrections and hedging, across everything collected from it. Not a measure of accuracy.
Outlets on this story
1
Environment
Same framing elsewhere
1
articles that frame the event the way this one does
Analyzed 2026-10-04 · how these are computed

How this is being covered How these are calculated →

Article leaning vs. publisher reliability
Source leaning vs. consistency

Publisher

Al Jazeera · 4467 article(s) · 2 correction(s) detected
Running correction rate · 2 correction(s)

Who wrote this

Arshak Makichyan
1 article(s) here · 1 carrying a prediction
🔮 The process, initially scheduled for completion in 2038, is now expected to continue until 2049.
The only article under this byline in the corpus.

Topics

Lithuania Rosatom Rosenergoatom Russia Soviet

Subjects

Russia GPE · 11× Lithuania GPE · 2× Rosatom ORG · 2× Rosenergoatom ORG · 2× Soviet NORP · 2× Bangladesh GPE · 1× Russian NORP · 1× Turkiye GPE · 1× USSR GPE · 1× Vladimir Putin PERSON · 1×

Narrative

This is what happened after the 1957 Mayak disaster, when the Soviet authorities concealed the accident and its consequences and did not publicly acknowledge the disaster until 1989, more than three decades later, while thousands of people were left to suffer the long-term consequences of radioactive contamination.
framing: assertive · carried by 1 article(s) · first seen 2026-10-04
🔮 The process, initially scheduled for completion in 2038, is now expected to continue until 2049.
2026-10-04 · Al Jazeera
Russia’s nuclear plants are ageing. Who will pay to dismantle them? · assertive framing

Claims (54 extracted, 4 hedged)

The world often discusses the nuclear threat posed by Russia, but far less attention is paid to the nuclear risks within Russia itself, particularly those posed by ageing nuclear power plants, some of whose reactors are already more than 50 years old. asserted
some → discuss → reactors
At the same time, Russia is building nuclear power plants around the world, from Turkiye to Bangladesh, while promoting nuclear energy as a “sustainable” alternative to fossil fuels. asserted
Russia → build → fuels
Russian President Vladimir Putin regularly meets with foreign leaders to discuss existing and potential nuclear projects. asserted
Putin → meet → projects
Yet one question remains largely overlooked: what happens to these nuclear facilities when they reach the end of their operational lives? asserted
they → overlook → lives
During the Soviet period, nuclear power plants were built across the USSR, including in Lithuania. asserted
plants → build → Lithuania
As part of Lithuania’s accession to the European Union, the country was required to shut down the two Soviet-built reactors at the Ignalina Nuclear Power Plant. asserted
country → require → Plant
The first reactor was closed in 2004 and the second in 2009. asserted
reactor → close → 2009
The decommissioning process has proved both extraordinarily expensive and time-consuming. asserted
process → prove → ?
By 2020, the estimated cost had reached 3.3 billion euros ($3.7bn), with only 49 percent of the planned work completed. asserted
percent → estimate → work
The process, initially scheduled for completion in 2038, is now expected to continue until 2049. asserted
process → schedule → 2049
Russia itself does not seem to be paying much attention to this question. asserted
Russia → seem → question
Rosenergoatom plans to decommission 35 reactors. asserted
Rosenergoatom → plan → reactors
Yet the company’s own estimates point to a funding shortfall of approximately 18.7 billion euros, while the total estimated cost of decommissioning is about 21 billion euros. asserted
cost → point → decommissioning
Actual decommissioning costs are usually significantly higher than initially projected. asserted
costs → project → ?
For example, the cost of decommissioning the former nuclear power plant in Lubmin, Germany, was initially estimated at 1 billion euros but is now estimated at 10 billion euros. asserted
cost → decommission → euros
For the time being, however, Russia appears to be postponing the most costly stages of decommissioning. asserted
Russia → appear → decommissioning
Rather than fully dismantling reactors soon after shutdown, it often places them in long-term “safe” storage, transferring much of the financial and technical burden into the future. asserted
it → dismantle → future
Deferred dismantling does not solve the problem, but merely postpones the costly stages of decommissioning, which is particularly concerning given Russia’s existing funding gap. asserted
which → solve → gap
Environmental NGO Bellona Foundation reports, based on Rosatom’s own projections, that by around 2037, Rosatom’s decommissioning and remediation obligations could exceed its net profit. uncertain
obligations → report → profit
Moreover, the longer decommissioning is delayed, the greater the associated financial, technical and safety risks are likely to become. asserted
risks → delay → ?
Russia has inherited approximately 774,000 cubic metres of radioactive waste from the Soviet Union. asserted
Russia → inherit → Union
The upcoming decommissioning of 36 reactor units at eight nuclear power plants is expected to generate an additional 800,000 cubic metres of radioactive waste. asserted
decommissioning → expect → waste
Russia already has experience of what happens when industries leave major environmental liabilities behind. asserted
industries → have → liabilities
In the Kemerovo region, where around half of Russia’s coal is produced, mountains of waste from coal mining scar the landscape. asserted
mountains → produce → landscape
Some of this waste burns, polluting nearby communities. asserted
Some → burn → communities
When coal companies go bankrupt, the cost of dealing with what they leave behind can fall to the state and local communities. asserted
they → go → communities
But nuclear waste and decommissioned reactors cannot simply be abandoned if the money runs out. asserted
money → decommission → ?
The question therefore becomes even more important as Russia’s economic situation deteriorates: what will happen to all these megaprojects if the money needed to maintain, decommission and eventually dismantle them is no longer available? asserted
money → become → them
The countries where Russia is building its numerous nuclear power plants should therefore think about what happens if these projects cannot be maintained or later decommissioned as planned. asserted
projects → build → plants
They need a Plan B in case something goes wrong in Russia. asserted
something → need → Russia
And, as history has repeatedly shown, Russia’s political situation can change unpredictably. asserted
situation → show → ?
The Chornobyl disaster demonstrated how the Soviet authorities’ attempts to suppress information and downplay the scale of the accident fuelled public distrust and disillusionment, contributing to growing social and political unrest in the late Soviet period. asserted
attempts → demonstrate → period
Today, Russia’s continued neglect of nuclear waste and repeated postponement of nuclear plant decommissioning could similarly create conditions for both another environmental catastrophe and growing social unrest, particularly if authorities once again respond to such a crisis with silence or attempts to conceal its scale. uncertain
authorities → repeat → scale
These risks are compounded by Russia’s deteriorating economic situation. asserted
risks → compound → situation
In an effort to sustain the war economy, the Russian government has also drastically weakened environmental regulations. asserted
government → sustain → regulations
National defence is now by far the largest single item in Russia’s federal budget, while environmental protection accounts for only a small fraction of government spending. asserted
protection → account → spending
Environmental disasters have repeatedly demonstrated that the Russian regime is unwilling to prioritise long-term environmental safety. asserted
regime → demonstrate → safety
Russia continues to operate an ageing shadow fleet to transport oil, and the environmental risks associated with that fleet were highlighted by the 2024 Black Sea oil spill, when two ageing Russian tankers released thousands of tonnes of fuel oil into the sea. asserted
tankers → continue → sea
The spill was described as the Black Sea region’s worst environmental disaster in decades. asserted
spill → describe → decades
This broader pattern of environmental negligence raises questions about how the country will manage its ageing nuclear infrastructure and the growing problem of nuclear waste. asserted
country → raise → waste
…and 14 more, not listed.
💬Give feedback
🕘History 🎫Support