Gov. Abigail Spanberger (D-VA) unveiled what she calls the nation’s “most comprehensive and aggressive” data center regulations in Virginia, aiming to hold companies accountable, reduce energy costs, and safeguard environmental protections.
asserted
companies → unveil → protections
Her executive order announcement came on the heels of a week centered on the topic of artificial intelligence, as Americans have increasingly raised concerns about the data center infrastructure powering AI, and top industry executives call for national guardrails on frontier AI development.
asserted
executives → come → development
As a Democratic governor of the state home to the most data centers in the country, Spanberger has navigated the data center debate throughout her first year in office by firmly opposing a full moratorium while also calling on companies to “pay their fair share.”
asserted
Spanberger → navigate → share
As the data center and AI regulation debate explodes across the country during the 2026 midterm elections, Spanberger signed a new executive order to provide more oversight in the data center industry.
asserted
Spanberger → explode → industry
“The policies put forth in this framework are the highest standards in America,” the governor said.
asserted
governor → put → America
“And they’re organized around five core requirements: increasing transparency, strengthening environmental protections, lowering energy costs, bolstering our clean energy economy, and delivering a better deal for Virginia workers.”
asserted
they → organize → workers
Transparency aims and environmental protections
Spanberger’s executive order includes several measures aimed at increasing communication and transparency between local communities and data center companies building in the region.
asserted
order → include → region
The executive order bans the state government from signing any nondisclosure agreements related to data centers and requires community-benefit agreements between companies and local communities.
asserted
order → ban → companies
Spanberger’s order also ends by-right approvals in the state, which have become a contentious topic as they allow projects to skip local government public hearings or votes if they meet all zoning and ordinance requirements.
asserted
they → end → requirements
The order requires companies to get permit approval from local governments for any data center that requires over 25 megawatts of electricity.
asserted
that → require → electricity
On the environmental and energy side of the order, Spanberger noted that the move will set “high standards” for data center emissions, water use, noise pollution, and land use.
asserted
move → note → emissions
The order requires the state government to review the emissions and air quality impacts of existing data centers and give existing centers ways to retrofit their facilities to meet new standards.
asserted
order → require → standards
The order gets the ball rolling on the state, providing model guidance for local communities to give data center companies that will measure their “anticipated electricity demand, water use, wastewater management, backup generation, air emissions, noise, traffic, public-service needs, and other material project impact.”
asserted
that → get → demand
Spanberger emphasized the policy prioritizing data centers that promise to develop with clean energy.
asserted
that → emphasize → energy
“We will prioritize grid access for data centers that source clean energy five years faster than the Clean Economy Act requires and reduce emissions from backup generators by 60 percent,” Spanberger said.
asserted
Spanberger → prioritize → percent
“We’re also going to limit the amount of electricity these facilities can generate from on-site natural gas, an important step that no other state has taken action on yet.”
asserted
state → go → action
Other provisions of the order
Spanberger also emphasized that Virginia’s data center policy will prioritize proposed data center projects that commit to hiring local workers and sourcing local raw materials.
asserted
that → emphasize → materials
“Virginians need access to good local jobs,” Spanberger said.
asserted
Spanberger → need → jobs
“That’s why this framework prioritizes the training and hiring of local workers, both for construction and long-term employment.
asserted
framework → ’ → construction
We’re also prioritizing Virginia-made, sustainable materials and technology in data center construction and grid infrastructure.
asserted
We → prioritize → construction
No moratorium on new centers
Spanberger did not, however, announce any bans on new data center projects, something states like New York and local areas like Virginia’s Loudoun County have moved to implement.
asserted
states → announce → County
She was asked about her decision not to implement a statewide moratorium on new projects during the press conference and told reporters that she is leaving that decision up to individual communities.
asserted
she → ask → communities
“As localities continue to have the option of choosing to reject or accept applications for data centers to come into their communities, it’s vital that the state actually provide a framework for them to be able to make those thoughtful, good decisions about what is important to their community,” Spanberger said.
asserted
Spanberger → continue → community
Republicans respond
asserted
Republicans → respond → ?
Senate Republican Leader Ryan McDougle said he is glad Spanberger is “finally talking about high power bills and data centers,” while Virginia’s House GOP Leader Terry Kilgore called Spanberger’s energy policy “contradictory”.
asserted
Kilgore → say → policy
Meanwhile, GOP State Sen. Glen Sturtevant, who has been vocal about his calls for a statewide moratorium, bashed Spanberger for not implementing a ban, saying she “sided with the Data Center industry.”
asserted
she → bash → industry